|
Thanks to Building
Manager Jim Kordish for furnishing the captions for the pictures below
which were taken by our construction consultants. |
 |
|
May 1 Deteriorated steel reinforcing bar
(rebar). |
 |
|
June 25 Deteriorated steel beam |
 |
|
June 25 First floor garage deck looking
through to lower level, after the concrete deck was removed. showing the
beams and rebar that remained. |
 |
|
June 26 View looking up from the lower
level at the underside of the first floor deck showing the forms in
place prior to the new concrete deck being poured. |
 |
|
June 26 Looking down from the first
floor at the forms (rusty, brown color) in place. |
 |
|
June 26 View from the first floor
showing replacement rebar in beams. |
 |
|
June 26 New rebar connecting “new”
concrete to “old”. |
 |
|
June 29 View of the first floor beams
prior to pouring new concrete deck. |
 |
|
June 30 View of first floor of our
garage while work is in progress, showing areas that had been removed
and areas that were not. |
 |
|
June 30 Shows the pipe used to pump the
concrete, running along the first floor towards the west end of the
garage. |
 |
|
July 7 View of lower level garage
showing the rubble from the first floor demolition. The “red ladders”
are scaffolding. |
 |
|
August 10 Exposed, deteriorated rebar
inside concrete beam. |
 |
|
August 10 Exposed, deteriorated steel
beam and column. |
 |
|
August 12 New rebar in place and ready
for concrete pour. |
 |
|
September 3 New concrete deck. |
 |
|
September 3 New rebar and forms in place
and ready for pouring concrete. Also shows a section of the “old” floor
deemed “ok” and therefore not removed. |
 |
|
October 19 New drains at the overhead
door entrance to our garage. |
 |
|
November 4 Exposed, deteriorated rebar. |
 |
|
November 5 Deteriorated floor drain and
piping - lower level. |
 |
|
November 6 New cleanout in floor drain
piping – lower level. |
 |
|
November 6 Lower level floor, just west
of ramp, showing new “fill” prior to pouring new concrete floor. |
 |
|
November 7 Lower level floor just west of
ramp, showing wire mesh installed prior to pouring new concrete floor. |
 |
|
November 7 Ramp (looking up from lower level)
showing wire mesh installed prior to pouring new concrete floor. |
|